BEST Time Block Schedule

Week Programming Mechanical BEST General
9/14 - 9/20 Set up Software, Orient to new system. Settle on Design by the end of the week Begin on brainstorming essay, decide on theme Kickoff Saturday, mettings Tuesday, Thursday. Sat. Recruit more teachers
9/21 - 9/27 Divide into groups and begin work on program Begin Building Finish/Revise brainstorm essay, begin on research paper, design booth and T-shirts, changes made to website decided on Outreach letter made; send out letter
9/28 - 10/4 Continue Work, plan for when done Build Website work, T-shirts ordered T-shirts must be ordered in order to meet deadline. Work on outreach
10/5 - 10/11 Finish Program Later stages of buid, document all tests Finish Notebook, revise, and work on presentation More outreach, make sure all activities are documented arrange transportation for Mall Day
10/12 - 10/18 Programs finished and selected, test on program on robot and revise Robot testing, all tests documented Notebooks due on 14th, T-shirts come in soon, booth complete assembled and tested Mall Day on Saturday, strong presence there needed, Notebook due on 14th, Website due on 17th
10/19 - 10/25 Small modifications based on tests and Mall Day findings Iron out all problems, make spare parts, prepare tools for pit area Practice interviews and presentations Game day Sat., assign positions for game day and arrange transportation